How to Run a Factory Acceptance Test (FAT) for an Imported Power Transformer

Published on November 25, 2026 - By TARIL Editorial Team

This guide covers preparation for a Factory Acceptance Test (FAT) for an imported power transformer, essential electrical tests, pre-shipment inspections, handling failed results, and the documentation needed to approve the unit for dispatch.

Introduction

To run a Factory Acceptance Test (FAT) for an imported power transformer, review the approved specifications, agree on the required tests, verify the results against acceptance criteria, and inspect the unit before shipment. Document any failures, confirm corrective actions, and approve dispatch only when all mandatory requirements are met.

Problems discovered after delivery can increase repair costs, delay installation, and require additional inspections. Conducting the FAT at the manufacturer's facility helps buyers identify issues before the transformer is shipped.

What Should You Prepare Before Starting a Power Transformer FAT?

Before testing, the buyer and manufacturer should agree on the scope, acceptance criteria, responsibilities, and required documentation.

Review these documents:

  • Purchase order and technical specification: Confirm rated power, voltage levels, frequency, impedance, cooling arrangement, and tolerances.
  • Approved drawings: Check winding connections, terminal arrangements, dimensions, and nameplate details.
  • Inspection and test plan (ITP): Identify mandatory tests, witness points, hold points, and required records.
  • Applicable standards: Confirm whether the contract specifies IEC, ANSI/IEEE, or national standards. IEC 60076-1 covers general requirements for power transformers, while IEC 60076-3 addresses insulation levels and dielectric tests. Verify the applicable standards and editions before the FAT.
  • Calibration records: Verify that testing instruments have suitable, valid calibration records.

Which Tests Should Be Included in a Power Transformer FAT?

Use the approved inspection plan to determine the required tests.

1. Electrical routine tests

According to IEC 60076-1, routine tests include checks such as:

  • Winding resistance: Measured values are corrected to a reference temperature and compared with design values and readings across the three phases for consistency.
  • Voltage ratio and phase displacement: Verifies the turns ratio and vector group against the nameplate. For 3-phase power transformers, this check confirms the windings are connected correctly.
  • Short-circuit impedance and load loss: Checks measured values against specified tolerances.
  • No-load loss and current: Measures core losses and excitation current against agreed limits.
  • Dielectric tests: Verify that the insulation withstands the prescribed test voltages without breakdown.
  • Tap-changer operation: Where fitted, verifies correct operation across specified tap positions.
  • Leak and tightness tests: Checks liquid-filled transformer tanks and seals for unacceptable leakage, as applicable.

Additional routine tests may apply depending on the transformer and contractual requirements.

2. Impulse, partial-discharge, type and special tests

Under IEC 60076-3, dielectric test requirements depend on the transformer's highest voltage for equipment (Um) and insulation category.

  • Lightning impulse test: Under IEC 60076-3:2013, Table 1, the full-wave test is a type test for uniformly insulated windings with Um ≤ 72.5 kV and a routine test for uniformly insulated windings above 72.5 kV up to 170 kV. For windings above 170 kV, the lightning impulse test is also a routine test, so every unit gets it.
  • Partial-discharge measurement: Partial-discharge measurement: Done during the induced voltage test to detect weak spots in the insulation. Under IEC 60076-3, it is a routine test for transformers above 72.5 kV. Confirm the acceptance limits in the contract.
  • Temperature-rise test: Evaluates winding and oil temperature rises; generally a type test.
  • Sound-level measurement: Checks operating noise when required by the specification or contract.

3. Functional checks

Check supplied controls and accessories, including tap changers, cooling controls, temperature indicators, alarms, and protective devices where fitted.

How Should You Inspect an Imported Transformer Before Shipment?

Compare the nameplate with the approved specification, checking the serial number, rated capacity, voltage levels, frequency, winding configuration, and other required details. Verify that the finished unit matches the drawings and includes all specified accessories.

Inspect for damaged bushings, loose fittings, corrosion, incomplete assembly, and other visible defects. For liquid-filled units, examine seals, valves, and fluid-level indications. For dry-type transformers, check accessible winding surfaces, insulation, supports, and ventilation arrangements.

What Extra Checks Are Needed Before Shipping an Imported Transformer?

Long-distance sea and road transport can expose transformers to vibration, impact, and moisture. Before dispatch, check the following:

  • Transport protection: Verify that the transformer is secured against movement and impact during transit.
  • Moisture protection: For large transformers shipped without oil, confirm that the tank is sealed and filled with dry air or nitrogen at the specified pressure to limit moisture ingress.
  • Shock recorder: Confirm that a shock or impact recorder is fitted where required. It records impacts during transit and helps identify possible rough handling.
  • Packaging and accessories: Ensure separately packed components are labelled, protected, and listed in the shipping inventory.
  • Handling and preservation: Obtain the manufacturer's instructions for lifting, storage, and transport, including any special requirements for liquid-filled units.

Overseas buyers can witness the FAT in person or appoint a local third-party inspector to attend on their behalf. Remote witnessing may also be possible if the manufacturer supports it and the contract permits it. Agree on the arrangements and inspection schedule in advance.

What Should You Do If a FAT Result Fails?

The manufacturer should record the non-conformity, investigate its cause, and propose corrective action. This may involve repairing a component, correcting a connection, adjusting a mechanism, or checking the test setup. After corrective work, repeat the affected test and record the results. Retain the original readings and corrective-action records for traceability. Withhold shipment approval if a mandatory test remains unsuccessful, a significant safety concern is unresolved, or required documents are missing. Any proposed deviation should be reviewed and approved in writing by the authorized buyer or engineer.

What Should the Final FAT Report Include?

Before signing the report, confirm that it includes:

  • Transformer identification and serial number.
  • Tests performed and applicable procedures.
  • Actual measurements and acceptance limits.
  • Test equipment details, where required.
  • Results, observations, and deviations.
  • Corrective actions and verification.
  • Required signatures and approval status.

Ensure the report identifies the exact unit purchased. Record outstanding tests or documents as open items. FAT approval does not eliminate receiving inspections or commissioning tests, since transportation, storage, and installation can introduce new issues.

What Should You Check With a Transformer Supplier Before the FAT?

Before scheduling a FAT, confirm that the power transformer manufacturer has the facilities, equipment, and procedures needed to perform the agreed tests. Ask the power transformer suppliers for their inspection and test plan, instrument calibration records, and sample test reports.

When assessing an electrical transformer manufacturer, verify that the testing scope matches the purchase specification and applicable IEC standards.

Conclusion

A successful FAT documents whether equipment meets agreed requirements and is ready for delivery. Clear acceptance criteria, verified results, and resolved non-conformities help buyers reduce uncertainty before the transformer reaches the installation site.

Planning a transformer FAT? Contact TARIL to discuss your inspection scope, testing requirements, and pre-shipment checks with our team before dispatch.

FAQs

1. Is a FAT required for every imported transformer? Not always. Requirements depend on the purchase contract, project specifications, applicable standards, and buyer's inspection requirements. Confirm the scope before manufacturing is completed.

2. How long does a transformer FAT take? The duration depends on the transformer design, required tests, inspection scope, and any issues found during testing. It varies from unit to unit, so ask the manufacturer for a written schedule before the FAT.

3. Are all transformer tests performed on every unit? No. Routine tests are generally performed on individual units as required by applicable standards. Type tests demonstrate design characteristics, while special tests depend on contractual requirements.

4. Can a transformer be shipped before the FAT report is approved? If the contract requires written approval before dispatch, shipment should wait until approval is granted. Alternative arrangements must be documented and authorized.

5. Who should witness a transformer FAT? The buyer may appoint an electrical engineer, quality inspector, or independent inspection agency. The manufacturer's team performs the agreed tests and supplies the records. The contract should clarify who can accept the results.